|
A Gym at Thousand Oaks By Freda Grones
Shade O'Quinn, AIA, the project architect, agrees. He said that the Monolithic Dome's resistance to storms was something their committee was not fully aware of until they began investigating.
"Initially, we thought about a pre-manufactured, metal building for a gymnasium," O'Quinn said. "The estimates for that project were around $800,000 for a 14,000 square foot activities building. That was over our budget."
[According to Gary Clark, MDI's vice-president of operations, single-phase electricity with a total of 220 volts is what is used in most homes. Three-phase electricity provides more voltage; it's usually best for running heavy-duty motors, large air conditioners, etc.]
"The campground only has single-phase electrical power," O'Quinn said. "To air condition a typical type of lightweight metal building, you need a lot of power. With single-phase electricity, we would have had to use many, many multiple, small single-phase units and many small air compressors outside." That created a greater initial expense and a greater on-going expense.
Other factors further complicated the situation. Instead of producing plans that included full design and specifications to be submitted to general contractors for bids, the committee preferred using Design-Build, an alternative method for doing a project. In Design-Build, a set of concept drawings is created that give a general idea of what is needed. A contractor is then chosen to work along with the design team to build the project.
"But we were not able to find a suitable general contractor," O'Quinn recalled. "Individuals we had worked with in the Dallas area were not too hip on working so far away and therefore their prices reflected that, and general contractors in the area, while good, were few." A somewhat discouraged committee began investigating domes, and eventually met with Larry Byrne, MDI's resident designer.
O'Quinn said that after taking a look at the Monolithic Dome process and product, "a few advantages" immediately appealed to the committee. "First of all, the simplistic nature of the structure really helped us out in the sense of doing a Design-Build project," O'Quinn said. "If we would have done it the traditional way (accepting the bid of a general contractor), we would have had to have many subcontractors to complete the project, but with a Monolithic Dome one source could build the shell.
"And the building shell itself is simplistic," O'Quinn continued. "The design is uncomplicated. So, we don't have to plan different types of insulation systems, different sidings. Before, we were questioning: do we go with brick, masonry units, metal, part brick and part metalon and on. There were so many variables that complicated the other structures. "The Monolithic Dome was very straightforward, so we felt very comfortable that by going with it, we would get a good product and everything we wanted within our budget restraints. That was a very important second advantage," O'Quinn said.
The third advantage O'Quinn cited had to do with the electrical power at Thousand Oaks. "This was a real biggy," he said. "Because of the dome's efficient insulation, we could heat and cool with single-phase power. That probably tipped the scale. We just had nightmares thinking of twenty small air conditioners to cool. The Monolithic Dome brought that down to possibly four units heating and cooling the whole facility. That was a big, big plus." A Monolithic Dome's ability to withstand tornadoes and high winds constituted the fourth advantage. Administrator Beaman said, "The fact that the dome provided a safe shelter really appealed to us. We presented all our findings to the church board, and they concurred." When completed this summer, Thousand Oaks' new gymnasium will include 15,273 square feet of floor area on the main level and 1,089 square feet in its mezzanine, at an estimated construction cost of $500,000. O'Quinn, who had not worked on Monolithic Dome projects before Thousand Oaks, said, "I have a traditional education and the dome is not a very common, traditional type of structure. But the more I understood it and as I got more involved, I came to really believe that the Monolithic Dome suits itself perfectly to this project. I'm really anxious to see more people use this type of structure for gyms; big, open assembly areas; churches and schools. It meets a lot of needs that traditional structures just don't. "I don't think the dome is the answer for every project," O'Quinn concluded, "but it sure makes a perfect gymnasium. We're excited to see ours finished."
|
||||||||||||||
|
|
||||||||||||||